Welcome to Westonci.ca, where finding answers to your questions is made simple by our community of experts. Discover detailed solutions to your questions from a wide network of experts on our comprehensive Q&A platform. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.

To compleate a task in 16 days a company needs 5 workers each working 6 hours per day
The company decides to have 8 people each working 4 hours per day
Assuming that each person works at the same rate
How many days will the task take to complete?