Discover the answers you need at Westonci.ca, where experts provide clear and concise information on various topics. Join our platform to connect with experts ready to provide accurate answers to your questions in various fields. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.

To compleate a task in 16 days a company needs 5 workers each working 6 hours per day
The company decides to have 8 people each working 4 hours per day
Assuming that each person works at the same rate
How many days will the task take to complete?