At Westonci.ca, we connect you with the answers you need, thanks to our active and informed community. Get quick and reliable solutions to your questions from a community of seasoned experts on our user-friendly platform. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.

a set of priority planning techniques for planning component items below the end item level is called:

Sagot :

The set of priority planning techniques for planning component items below the end item level is called as material requirements planning (MRP).

MRP is the system which establishes a schedule plan that illustrates the quantity of components required at each level of assembly and, based on lead times, calculates the time when these components will be needed. It helps to avoid the missing errors. This system also helps to evaluate the time needed for shipping the whole set of items. However it faces some limitations related to inventory management, quality control, supply demand etc. The other three inputs of an MRP system are given below:

  1. Master Production Schedule (MPS)
  2. Inventory Status File (ISF)
  3. Bill of Materials (BOM)

Learn more about MRP at:

brainly.com/question/24370075

#SPJ4

To refer to complete question, see below:

A set of priority planning techniques for planning component items below the end item level is called:

A) master scheduling

B) material requirements planning

C) capacity planning

D) production control

E) none of the above