Explore Westonci.ca, the leading Q&A site where experts provide accurate and helpful answers to all your questions. Our platform connects you with professionals ready to provide precise answers to all your questions in various areas of expertise. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.

a project has five activities: a through e. a is an immediate predecessor of c and of d. b is also an immediate predecessor of c and of d. c and d are both immediate predecessors of e. how many paths are there on the project diagram?

Sagot :

There are four paths in this network of critical path method based on the diagram.

What is critical path method?

The critical path method (CPM) is a method for determining schedule flexibility and identifying tasks required for project completion. The longest series of tasks that must be completed on schedule for the project to be concluded is known as a critical path in project management. The rest of the project will be delayed if important activities are delayed.

Finding the most crucial activities in the project timetable, determining task dependencies, and computing.

To know more about critical path method, check out:

https://brainly.com/question/24227953

#SPJ4

Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. Your questions are important to us at Westonci.ca. Visit again for expert answers and reliable information.