Explore Westonci.ca, the leading Q&A site where experts provide accurate and helpful answers to all your questions. Get quick and reliable answers to your questions from a dedicated community of professionals on our platform. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.
Sagot :
The activity variance for plane operating costs in October would be closest to $4,727 F .
Option D is correct.
Activity variance :
Activity deviation is the difference. Between a revenue or cost item in a variable budget and the same item in a static plan budget. Performance deviation arises only from the difference between the actual service coverage of the flexible budget and the expected service coverage of the planning budget.
Evaluating activity variance :
Plane operating costs in planning budget   :
                          = 48840+(2381 × 63)+(7× 293)
                                 $ 200894
Less: Plane operating costs in flexible budget
                = 48840+(2381 × 61)+(7× 298)
                     $196167
Activity variance for Plane operating costs = Â $200,894 - $196,167
                                   =  $4,727.
 Â
Activity variance is $4,727 F .
What is the purpose of activity variance?
Differences in activity are important for managerial decision-making. This is the difference between static and flexible budget cost items. This shows the cost difference between planned and flexible budgets.
Learn more about activity variance :
brainly.com/question/29704119
#SPJ4
We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Keep exploring Westonci.ca for more insightful answers to your questions. We're here to help.