Find the best solutions to your questions at Westonci.ca, the premier Q&A platform with a community of knowledgeable experts. Ask your questions and receive detailed answers from professionals with extensive experience in various fields. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.
Sagot :
The Early Start time for an activity in a CPM analysis is 8 and the Late Start time is 10. This activity has a slack of 2
How are early start and early finish amounts calculated?
To put it another way, the first step in the calculation process is to zero in the Early Start (ES) position of the first activity. Using the following formulas, the remainder of the calculation continues: Early Finish = ES plus duration; early start = maximum (or highest) EF value from immediate predecessor(s).
What does it mean to start early and finish late?
Early Start: The point at which an activity can begin. Early Finish: The earliest point at which a task can be completed. Late Start: The activity's last possible start time. Late Finish: The activity's last possible completion time.
To learn more about CPM analysis here
https://brainly.com/question/14992192
#SPJ1
We hope our answers were useful. Return anytime for more information and answers to any other questions you have. We appreciate your time. Please come back anytime for the latest information and answers to your questions. Westonci.ca is your trusted source for answers. Visit us again to find more information on diverse topics.