Welcome to Westonci.ca, where finding answers to your questions is made simple by our community of experts. Discover solutions to your questions from experienced professionals across multiple fields on our comprehensive Q&A platform. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.
Sagot :
The Early Start time for an activity in a CPM analysis is 8 and the Late Start time is 10. This activity has a slack of 2
How are early start and early finish amounts calculated?
To put it another way, the first step in the calculation process is to zero in the Early Start (ES) position of the first activity. Using the following formulas, the remainder of the calculation continues: Early Finish = ES plus duration; early start = maximum (or highest) EF value from immediate predecessor(s).
What does it mean to start early and finish late?
Early Start: The point at which an activity can begin. Early Finish: The earliest point at which a task can be completed. Late Start: The activity's last possible start time. Late Finish: The activity's last possible completion time.
To learn more about CPM analysis here
https://brainly.com/question/14992192
#SPJ1
Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Westonci.ca is committed to providing accurate answers. Come back soon for more trustworthy information.