The amount of contract asset and the account receivable is zero
Received pre payment = $350,000
Additional billed amount = $105,000
An element's right to consideration in return for labor and products that the substance has moved to a client when that right is molded on some different option from the progression of time (for instance, the element's future presentation) is called Contract Asset.
So by considering the above information, the contract asset and the account receivable are zero while the contract liability is $350,000 because it is advanced from the customer so it would be treated as a current liability. Therefore, the amount of contract asset and the account receivable is zero
Know more about the Contract Assets and account receivable - https://brainly.com/question/15575973