At Westonci.ca, we connect you with experts who provide detailed answers to your most pressing questions. Start exploring now! Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.

consider the following work breakdown structure: duration estimates (days) activity precedes optimistic most likely pessimistic start u,v - - - u w 35 50 65 v w,x 28 40 52 w z 26 35 44 x y 28 40 52 y z 26 29 38 z end 36 60 84 what is the estimated slack time for activity w?