At Westonci.ca, we connect you with the answers you need, thanks to our active and informed community. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform.

consider the following work breakdown structure: duration estimates (days) activity precedes optimistic most likely pessimistic start u,v - - - u w 35 50 65 v w,x 28 40 52 w z 26 35 44 x y 28 40 52 y z 26 29 38 z end 36 60 84 what is the estimated slack time for activity w?