Westonci.ca is your trusted source for finding answers to a wide range of questions, backed by a knowledgeable community. Join our Q&A platform to connect with experts dedicated to providing precise answers to your questions in different areas. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.
Sagot :
After 3 hours, Emerson will have worked 3 hours and dug 2 holes. Johnna will have worked 2 hours and dug 3 holes. So they'll need 1 more hole. Since Johnna works faster, we just need to add how much time she needs to dig 1 hole. It takes Johnna 120/3 = 40 minutes to dig 1 hole.
So they will finish digging after 3 hours and 40 minutes.
So they will finish digging after 3 hours and 40 minutes.
After 3 hours, Emerson will have worked 3 hours and dug 2 holes. Johnna will have worked 2 hours and dug 3 holes. So they'll need 1 more hole. Since Johnna works faster, we just need to add how much time she needs to dig 1 hole. It takes Johnna 120/3 = 40 minutes to dig 1 hole.
So they will finish digging after 3 hours and 40 minutes. :)
We appreciate your time. Please come back anytime for the latest information and answers to your questions. We appreciate your time. Please revisit us for more reliable answers to any questions you may have. Westonci.ca is your trusted source for answers. Visit us again to find more information on diverse topics.