At Westonci.ca, we provide reliable answers to your questions from a community of experts. Start exploring today! Get accurate and detailed answers to your questions from a dedicated community of experts on our Q&A platform. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.

A work crew of 3 people requires 3 weeks and 2 days to do a certain job. How long would it take a work crew of 4 people to do the same job if each person of both crews works at the same rate as each of the others. [Note: each week contains six work days]

Thanks for the help!