Explore Westonci.ca, the top Q&A platform where your questions are answered by professionals and enthusiasts alike. Join our platform to connect with experts ready to provide accurate answers to your questions in various fields. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.

A work crew of 3 people requires 3 weeks and 2 days to do a certain job. How long would it take a work crew of 4 people to do the same job if each person of both crews works at the same rate as each of the others. [Note: each week contains six work days]