Westonci.ca connects you with experts who provide insightful answers to your questions. Join us today and start learning! Our platform provides a seamless experience for finding precise answers from a network of experienced professionals. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.

A work crew of 3 people requires 3 weeks and 2 days to do a certain job. How long would it take a work crew of 4 people to do the same job if each person of both crews works at the same rate as each of the others. [Note: each week contains six work days]

Thanks for the help!