Welcome to Westonci.ca, your one-stop destination for finding answers to all your questions. Join our expert community now! Our Q&A platform offers a seamless experience for finding reliable answers from experts in various disciplines. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently.
Sagot :
First, we need to make two assumptions:
1). Assume that all diggers dig at the same rate.
2). Assume that the time required is directly proportional to the
length of the ditch. In other words, no matter how long or short
a ditch is, each inch of it takes the same amount of time to dig.
============================================
6 people take 4 days to dig 10 feet.
Half as many people do half as much work in the same length of time.
3 people take 4 days to dig 5 feet.
Wow ! That's the question you asked, so there's no more to calculate.
Your visit means a lot to us. Don't hesitate to return for more reliable answers to any questions you may have. Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. Thank you for visiting Westonci.ca, your go-to source for reliable answers. Come back soon for more expert insights.