Welcome to Westonci.ca, your ultimate destination for finding answers to a wide range of questions from experts. Our platform provides a seamless experience for finding precise answers from a network of experienced professionals. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.

it takes 24 days for four men to paint a building, how long will it take six men
to Paint the same building?

Sagot :

Answer:

hello

Step-by-step explanation:

4 men×24 days=96 man-days

96/6 = 16

it will take six men 16 days to paint the building.