Westonci.ca offers fast, accurate answers to your questions. Join our community and get the insights you need now. Discover solutions to your questions from experienced professionals across multiple fields on our comprehensive Q&A platform. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.
Sagot :
Final answer:
To find out how long it takes different numbers of workers to complete a job based on worker-days when 6 workers can finish it in 3 days.
Explanation:
To determine how long it would take a different number of workers to complete the same job, you can use the concept of 'worker-days.' Since 6 workers can finish the job in 3 days, the total worker-days needed is 6 workers * 3 days = 18 worker-days.
(a) For 4 workers: If the total worker-days needed is 18 and now there are 4 workers, the number of days would be 18 worker-days / 4 workers = 4.5 days to finish the job.
(b) For 8 workers: Similarly, with 8 workers, it would take 18 worker-days / 8 workers = 2.25 days to complete the job.
Learn more about Time calculcations for completing a job with different number of workers here:
https://brainly.com/question/42996087
Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Discover more at Westonci.ca. Return for the latest expert answers and updates on various topics.