At Westonci.ca, we make it easy for you to get the answers you need from a community of knowledgeable individuals. Explore thousands of questions and answers from knowledgeable experts in various fields on our Q&A platform. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.

You are working on the implementation of the smart traffic signal. The project has been completed about 2 months later than expected at a cost 2.5% lower than the budget. Which one of the following will you not undertake?
a. Resolve outstanding invoices
b. Obtain all outstanding operational documents
c. Meet all regulatory requirements
d. Calculate qualitative risk for the project