Westonci.ca is the best place to get answers to your questions, provided by a community of experienced and knowledgeable experts. Our platform provides a seamless experience for finding reliable answers from a knowledgeable network of professionals. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.

You are working on the implementation of the smart traffic signal. The project has been completed about 2 months later than expected at a cost 2.5% lower than the budget. Which one of the following will you not undertake?
a. Resolve outstanding invoices
b. Obtain all outstanding operational documents
c. Meet all regulatory requirements
d. Calculate qualitative risk for the project