Explore Westonci.ca, the premier Q&A site that helps you find precise answers to your questions, no matter the topic. Join our platform to connect with experts ready to provide precise answers to your questions in various areas. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.

A new recreational area in a different town will take 15 full-time (40 hours per week) workers 2 weeks to complete. In addition, the cost of materials is expected to be $77,718. Suppose in this town, there is some unemployment and the town pays 15 formerly unemployed workers to do the labor at the value of their leisure time, which is $14 per hour. What is the total opportunity cost of the project in this town?