Westonci.ca is the best place to get answers to your questions, provided by a community of experienced and knowledgeable experts. Experience the ease of finding quick and accurate answers to your questions from professionals on our platform. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.

The following project is at the end of its 6th week. Find the cost and schedule variances. Also, find the CPI and SPI. Then find the critical ratio of the project using earned value calculations.

Finally, calculate the ETC and EAC for the project.

Activity Predecessor Duration (wks) Budget ($) Actual Cost ($) % Complete
a - 2 300 400 100
b - 3 200 180 100
c a 2 250 300 100
d a 5 600 400 20
e b,c 4 400 200 20