Welcome to Westonci.ca, the ultimate question and answer platform. Get expert answers to your questions quickly and accurately. Discover solutions to your questions from experienced professionals across multiple fields on our comprehensive Q&A platform. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

If an activity's progress is defined as 0% until the activity is complete, the project manager is using:

a. The 50/50 rule
b. The all or nothing rule
c. The 0/100 rule
d. The Do Not Pass Go rule