Discover the answers to your questions at Westonci.ca, where experts share their knowledge and insights with you. Ask your questions and receive detailed answers from professionals with extensive experience in various fields. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

If an activity's progress is defined as 0% until the activity is complete, the project manager is using:

a. The 50/50 rule
b. The all or nothing rule
c. The 0/100 rule
d. The Do Not Pass Go rule


Sagot :

We appreciate your visit. Hopefully, the answers you found were beneficial. Don't hesitate to come back for more information. We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. We're dedicated to helping you find the answers you need at Westonci.ca. Don't hesitate to return for more.