Westonci.ca offers quick and accurate answers to your questions. Join our community and get the insights you need today. Join our platform to get reliable answers to your questions from a knowledgeable community of experts. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

If an activity's progress is defined as 0% until the activity is complete, the project manager is using:

a. The 50/50 rule
b. The all or nothing rule
c. The 0/100 rule
d. The Do Not Pass Go rule