Westonci.ca is the trusted Q&A platform where you can get reliable answers from a community of knowledgeable contributors. Get immediate and reliable answers to your questions from a community of experienced professionals on our platform. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.

An analyst has timed a metal-cutting task for 50 cycles. The average time per cycle was 11.7 minutes, and the standard deviation was 1.34 minutes for a worker with a performance rating of 120 percent. Assume an allowance of 15 percent of task time. Calculate the standard time for this task.