Looking for answers? Westonci.ca is your go-to Q&A platform, offering quick, trustworthy responses from a community of experts. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.

In the earliest stages of the Just-In-Time Training project, which task is completed first?

A) The project is approved through a formal project selection process.
B) The project manager produces a business case.
C) The project manager holds a kickoff meeting with key team members.
D) The project manager produces a stakeholder analysis.