At Westonci.ca, we make it easy to get the answers you need from a community of informed and experienced contributors. Our platform provides a seamless experience for finding precise answers from a network of experienced professionals. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.
Sagot :
Sure! Let's walk through solving this problem step-by-step.
1. Understand the Problem:
- We have 20 people who can complete a certain amount of work in 3 days.
- We need to determine how many people are needed to complete the same amount of work in 2 days.
2. Total Work Calculation:
- The total amount of work can be thought of in "person-days," meaning how much work one person could do in one day.
- With 20 people working for 3 days, the total amount of work is:
[tex]\[ \text{Total work} = 20 \text{ people} \times 3 \text{ days} = 60 \text{ person-days} \][/tex]
3. Determine People Required for 2 Days:
- If we want to complete 60 person-days of work in 2 days, we need to find the number of people required.
- Let [tex]\( P \)[/tex] represent the number of people needed to complete this work in 2 days. The total work would then be:
[tex]\[ \text{Total work} = P \text{ people} \times 2 \text{ days} = 60 \text{ person-days} \][/tex]
4. Solve for [tex]\( P \)[/tex]:
- Rearranging the equation to solve for [tex]\( P \)[/tex]:
[tex]\[ P = \frac{60 \text{ person-days}}{2 \text{ days}} = 30 \text{ people} \][/tex]
5. Conclusion:
- Therefore, to complete the same amount of work in 2 days, you would need 30 people.
Hence, the number of people required to complete the work in 2 days is 30.
1. Understand the Problem:
- We have 20 people who can complete a certain amount of work in 3 days.
- We need to determine how many people are needed to complete the same amount of work in 2 days.
2. Total Work Calculation:
- The total amount of work can be thought of in "person-days," meaning how much work one person could do in one day.
- With 20 people working for 3 days, the total amount of work is:
[tex]\[ \text{Total work} = 20 \text{ people} \times 3 \text{ days} = 60 \text{ person-days} \][/tex]
3. Determine People Required for 2 Days:
- If we want to complete 60 person-days of work in 2 days, we need to find the number of people required.
- Let [tex]\( P \)[/tex] represent the number of people needed to complete this work in 2 days. The total work would then be:
[tex]\[ \text{Total work} = P \text{ people} \times 2 \text{ days} = 60 \text{ person-days} \][/tex]
4. Solve for [tex]\( P \)[/tex]:
- Rearranging the equation to solve for [tex]\( P \)[/tex]:
[tex]\[ P = \frac{60 \text{ person-days}}{2 \text{ days}} = 30 \text{ people} \][/tex]
5. Conclusion:
- Therefore, to complete the same amount of work in 2 days, you would need 30 people.
Hence, the number of people required to complete the work in 2 days is 30.
Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. We're dedicated to helping you find the answers you need at Westonci.ca. Don't hesitate to return for more.