Westonci.ca offers quick and accurate answers to your questions. Join our community and get the insights you need today. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.

A project integrates with several systems developed by various vendors and one of these vendors has gone out of business. What should the project manager do first?
A. Meet with this vendor to identify a replacement.
B. Review the risk register and update the issue log.
C. Calculate the delay and notify the project sponsor of the new timeline.
D. Negotiate with another vendor to produce the deliverable.