At Westonci.ca, we connect you with the answers you need, thanks to our active and informed community. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.

Which project lifecycle allows only a single delivery?

A. Functional
B. Incremental
C. None of the above
D. Predictive

Sagot :

Final answer:

The Predictive project lifecycle allows only one delivery, with predetermined scope, cost, and timeline.


Explanation:

Predictive project lifecycle allows only a single delivery. In this approach, the project scope, cost, and timeline are determined at the beginning, and the final product is delivered all at once upon completion.