Get reliable answers to your questions at Westonci.ca, where our knowledgeable community is always ready to help. Join our platform to connect with experts ready to provide accurate answers to your questions in various fields. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.

You are evaluating two projects. You may accept only one of them. Project one will cost $379,000 initially and will pay $134,000 each year for the next 5 years. Project two will cost $454,000 initially, but will pay $101,000 for the next 10 years. The firm's cost of capital is 15%. Compute the NPV of each project. Which project has the highest NPV and by how much? Round your answers to the nearest dollar.
Group of answer choices

Project 1 has a higher NPV by $37,636.

Project 2 has a higher NPV by $37,636.

Project 2 has a higher NPV by $17,293.

Project 1 has a higher NPV by $17,293.

The two projects have equal NPV.