Welcome to Westonci.ca, where finding answers to your questions is made simple by our community of experts. Find reliable answers to your questions from a wide community of knowledgeable experts on our user-friendly Q&A platform. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.

¿Cuántos obreros se necesitan para realizar una obra en 170 días si 125 obreros la realizan en 250 días?

Sagot :

Final answer:

To calculate the number of workers needed for a project in 170 days based on the work done by 125 workers in 250 days, apply the concept of work done.


Explanation:

To solve the problem of determining the number of workers needed to complete a similar project in 170 days, you can use the concept of work done. In this case, since 125 workers complete the first project in 250 days, you can calculate the total work done for that project. Then, using the total work and the new time frame of 170 days, you can determine the number of workers needed.


Learn more about Work done and labor calculation here:

https://brainly.com/question/33403329