Welcome to Westonci.ca, where curiosity meets expertise. Ask any question and receive fast, accurate answers from our knowledgeable community. Join our platform to connect with experts ready to provide accurate answers to your questions in various fields. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.

Due to shortage of resources, a project manager has made a decision in a 3-year construction project to develop a partial work break down structure (WBS) in the beginning of the planning phase. The WBS will be expanded as more information is known in the near term. What should the project manager do if a key resource criticizes her decision to develop the partial WBS?
A. Ignore the resource's comments
B. Remove the resource from the project
C. Re-develop the complete work breakdown structure for all 3 years
D. Explain to the resource about the Rolling wave planning