Get the answers you need at Westonci.ca, where our expert community is always ready to help with accurate information. Get quick and reliable solutions to your questions from knowledgeable professionals on our comprehensive Q&A platform. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.

Calculate EVM metrics for the following test problems: Plan at End of 2nd Quarter: Tasks 1, 3, 5 and 6 should be completed, Tasks 2 and 4 should be 96 percent complete, and Task 7 should be 51 percent complete. Results at End of 2nd Quarter: Tasks 1, 3, 5, and 6 have been completed, Task 2 is 50 percent complete, Task 4 has not been started, and Task 7 is 10 percent complete. $137,500 has been charged to the project.