Discover answers to your most pressing questions at Westonci.ca, the ultimate Q&A platform that connects you with expert solutions. Join our platform to connect with experts ready to provide precise answers to your questions in different areas. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.

Calculate EVM metrics for the following test problems: Plan at End of 2nd Quarter: Tasks 1, 3, 5 and 6 should be completed, Tasks 2 and 4 should be 96 percent complete, and Task 7 should be 51 percent complete. Results at End of 2nd Quarter: Tasks 1, 3, 5, and 6 have been completed, Task 2 is 50 percent complete, Task 4 has not been started, and Task 7 is 10 percent complete. $137,500 has been charged to the project.