At Westonci.ca, we make it easy to get the answers you need from a community of informed and experienced contributors. Get quick and reliable solutions to your questions from a community of seasoned experts on our user-friendly platform. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.

In an adaptive project, it is up to the product owner to decide when the project has gone as far as is necessary, based on_____
a. The WBS
b. The final product, service, or result
c. The "definition of done"
d. The product backlog