Welcome to Westonci.ca, the ultimate question and answer platform. Get expert answers to your questions quickly and accurately. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.

In an adaptive project, it is up to the product owner to decide when the project has gone as far as is necessary, based on_____
a. The WBS
b. The final product, service, or result
c. The "definition of done"
d. The product backlog