Discover a wealth of knowledge at Westonci.ca, where experts provide answers to your most pressing questions. Join our Q&A platform and connect with professionals ready to provide precise answers to your questions in various areas. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.
Sagot :
Certainly! Let's determine the crashing cost per day for each activity in the project based on the provided data, under the assumption that Activity D cannot be shortened.
### Given Table Data
Here is the relevant data extracted from the table:
- Activity B
- Normal Duration: 17 days
- Normal Cost: 100 million
- Crashed Duration: 3 days
- Crashed Cost: 1500 million
- Activity C
- Normal Duration: 1 day
- Normal Cost: 700 million
- Crashed Duration: 6 days
- Crashed Cost: 1000 million
- Activity D
- Normal Duration: 5 days
- Normal Cost: 1500 million
- Crashed Duration: 5 days (cannot be shortened)
- Crashed Cost: 1500 million
- Activity G
- Normal Duration: 6 days
- Normal Cost: 2400 million
- Crashed Duration: 4 days
- Crashed Cost: 3000 million
### Step-by-Step Solution:
#### Activity B
1. Normal Duration: 17 days
2. Normal Cost: 100 million
3. Crashed Duration: 3 days (can reduce by 14 days)
4. Crashed Cost: 1500 million
- Crashing Cost per Day:
[tex]\[ \text{Crashing Cost per Day} = \frac{\text{Crashed Cost} - \text{Normal Cost}}{\text{Normal Duration} - \text{Crashed Duration}} \][/tex]
[tex]\[ \text{Crashing Cost per Day} = \frac{1500 - 100}{17 - 3} = \frac{1400}{14} = 100 \text{ million} \][/tex]
#### Activity C
In this case, the normal duration is less than the crashed duration (i.e., crashing implies an increase in the duration), hence calculations for crashing cost are not needed. We'll consider the crashing cost per day as 0.
#### Activity D
Since Activity D cannot be shortened, the crashing cost per day is 0.
#### Activity G
1. Normal Duration: 6 days
2. Normal Cost: 2400 million
3. Crashed Duration: 4 days (can reduce by 2 days)
4. Crashed Cost: 3000 million
- Crashing Cost per Day:
[tex]\[ \text{Crashing Cost per Day} = \frac{\text{Crashed Cost} - \text{Normal Cost}}{\text{Normal Duration} - \text{Crashed Duration}} \][/tex]
[tex]\[ \text{Crashing Cost per Day} = \frac{3000 - 2400}{6 - 4} = \frac{600}{2} = 300 \text{ million} \][/tex]
### Final Crashing Costs per Day:
- Activity B: 100 million per day
- Activity C: 0 million per day
- Activity D: 0 million per day (cannot be shortened)
- Activity G: 300 million per day
So, the crashing costs for each activity are:
[tex]\[ \{\text{B}: 100 \text{ million per day}, \text{C}: 0 \text{ million per day}, \text{D}: 0 \text{ million per day}, \text{G}: 300 \text{ million per day}\} \][/tex]
In conclusion,
[tex]\[ \boxed{\text{B} = 100 \text{ million/day}, \text{C} = 0 \text{ million/day}, \text{D} = 0 \text{ million/day}, \text{G} = 300 \text{ million/day}} \][/tex]
### Given Table Data
Here is the relevant data extracted from the table:
- Activity B
- Normal Duration: 17 days
- Normal Cost: 100 million
- Crashed Duration: 3 days
- Crashed Cost: 1500 million
- Activity C
- Normal Duration: 1 day
- Normal Cost: 700 million
- Crashed Duration: 6 days
- Crashed Cost: 1000 million
- Activity D
- Normal Duration: 5 days
- Normal Cost: 1500 million
- Crashed Duration: 5 days (cannot be shortened)
- Crashed Cost: 1500 million
- Activity G
- Normal Duration: 6 days
- Normal Cost: 2400 million
- Crashed Duration: 4 days
- Crashed Cost: 3000 million
### Step-by-Step Solution:
#### Activity B
1. Normal Duration: 17 days
2. Normal Cost: 100 million
3. Crashed Duration: 3 days (can reduce by 14 days)
4. Crashed Cost: 1500 million
- Crashing Cost per Day:
[tex]\[ \text{Crashing Cost per Day} = \frac{\text{Crashed Cost} - \text{Normal Cost}}{\text{Normal Duration} - \text{Crashed Duration}} \][/tex]
[tex]\[ \text{Crashing Cost per Day} = \frac{1500 - 100}{17 - 3} = \frac{1400}{14} = 100 \text{ million} \][/tex]
#### Activity C
In this case, the normal duration is less than the crashed duration (i.e., crashing implies an increase in the duration), hence calculations for crashing cost are not needed. We'll consider the crashing cost per day as 0.
#### Activity D
Since Activity D cannot be shortened, the crashing cost per day is 0.
#### Activity G
1. Normal Duration: 6 days
2. Normal Cost: 2400 million
3. Crashed Duration: 4 days (can reduce by 2 days)
4. Crashed Cost: 3000 million
- Crashing Cost per Day:
[tex]\[ \text{Crashing Cost per Day} = \frac{\text{Crashed Cost} - \text{Normal Cost}}{\text{Normal Duration} - \text{Crashed Duration}} \][/tex]
[tex]\[ \text{Crashing Cost per Day} = \frac{3000 - 2400}{6 - 4} = \frac{600}{2} = 300 \text{ million} \][/tex]
### Final Crashing Costs per Day:
- Activity B: 100 million per day
- Activity C: 0 million per day
- Activity D: 0 million per day (cannot be shortened)
- Activity G: 300 million per day
So, the crashing costs for each activity are:
[tex]\[ \{\text{B}: 100 \text{ million per day}, \text{C}: 0 \text{ million per day}, \text{D}: 0 \text{ million per day}, \text{G}: 300 \text{ million per day}\} \][/tex]
In conclusion,
[tex]\[ \boxed{\text{B} = 100 \text{ million/day}, \text{C} = 0 \text{ million/day}, \text{D} = 0 \text{ million/day}, \text{G} = 300 \text{ million/day}} \][/tex]
Visit us again for up-to-date and reliable answers. We're always ready to assist you with your informational needs. Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. We're dedicated to helping you find the answers you need at Westonci.ca. Don't hesitate to return for more.