At Westonci.ca, we connect you with the answers you need, thanks to our active and informed community. Get detailed and precise answers to your questions from a dedicated community of experts on our Q&A platform. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.
Sagot :
To determine the crashing cost per day for each activity in the project, we need to follow these steps:
1. Understand the given data:
- Each activity has a normal duration (in days) and a normal cost (in million).
- Each activity also has a crashed duration (in days) and a crashed cost (in million).
- Crashing involves shortening the activity's duration at an increased cost.
2. Calculate the crashing cost per day:
- For each activity that can be crashed, compute the crashing cost per day using the formula:
[tex]\[ \text{Crashing cost per day} = \frac{\text{Crashed cost} - \text{Normal cost}}{\text{Normal duration} - \text{Crashed duration}} \][/tex]
3. Apply the formula to each activity and determine the crashing costs.
### Given Data and Calculation:
1. Activity A:
- Normal duration: 5 days
- Normal cost: 100 million
- Crashed duration: 3 days
- Crashed cost: 1500 million
[tex]\[ \text{Crashing cost per day for A} = \frac{1500 - 100}{5 - 3} = \frac{1400}{2} = 700 \text{ million per day} \][/tex]
2. Activity B:
- Normal duration: 7 days
- Normal cost: 700 million
- Crashed duration: 6 days
- Crashed cost: 0 million (not given, assume it is 0 for calculation)
[tex]\[ \text{Crashing cost per day for B} = \frac{0 - 700}{7 - 6} = \frac{-700}{1} = -700 \text{ million per day} \][/tex]
3. Activity C:
- Normal duration: 3 days
- Normal cost: 0 million (not given, assume it is 0 for calculation)
- Crashed duration: None (not given, assume it is same as normal duration)
[tex]\[ \text{Crashing cost per day for C} = 0 \text{ million per day} \][/tex]
4. Activity D:
- Since Activity D cannot be shortened, we do not calculate the crashing cost for it.
5. Activity E:
- Normal duration: 9 days
- Normal cost: 3750 million
- Crashed duration: 6 days
- Crashed cost: 9000 million
[tex]\[ \text{Crashing cost per day for E} = \frac{9000 - 3750}{9 - 6} = \frac{5250}{3} = 1750 \text{ million per day} \][/tex]
6. Activity F:
- Normal duration: 4 days
- Normal cost: 0 million (not given, assume it is 0 for calculation)
- Crashed duration: None (not given, assume it is same as normal duration)
[tex]\[ \text{Crashing cost per day for F} = 0 \text{ million per day} \][/tex]
7. Activity G:
- Normal duration: None (not given, assume it is same as crashed duration)
- Normal cost: 1600 million
- Crashed duration: 3 days
- Crashed cost: 2500 million
[tex]\[ \text{Crashing cost per day for G} = 0 \text{ million per day} \][/tex]
8. Activity H:
- Normal duration: 8 days
- Normal cost: 9000 million
- Crashed duration: 5 days
- Crashed cost: 15000 million
[tex]\[ \text{Crashing cost per day for H} = \frac{15000 - 9000}{8 - 5} = \frac{6000}{3} = 2000 \text{ million per day} \][/tex]
### Summary of Crashing Costs per Day for Each Activity:
- Activity A: 700 million per day
- Activity B: -700 million per day
- Activity C: 0 million per day
- Activity D: Not applicable (cannot be shortened)
- Activity E: 1750 million per day
- Activity F: 0 million per day
- Activity G: 0 million per day
- Activity H: 2000 million per day
Thus, these are the crashing costs for each activity in the project.
1. Understand the given data:
- Each activity has a normal duration (in days) and a normal cost (in million).
- Each activity also has a crashed duration (in days) and a crashed cost (in million).
- Crashing involves shortening the activity's duration at an increased cost.
2. Calculate the crashing cost per day:
- For each activity that can be crashed, compute the crashing cost per day using the formula:
[tex]\[ \text{Crashing cost per day} = \frac{\text{Crashed cost} - \text{Normal cost}}{\text{Normal duration} - \text{Crashed duration}} \][/tex]
3. Apply the formula to each activity and determine the crashing costs.
### Given Data and Calculation:
1. Activity A:
- Normal duration: 5 days
- Normal cost: 100 million
- Crashed duration: 3 days
- Crashed cost: 1500 million
[tex]\[ \text{Crashing cost per day for A} = \frac{1500 - 100}{5 - 3} = \frac{1400}{2} = 700 \text{ million per day} \][/tex]
2. Activity B:
- Normal duration: 7 days
- Normal cost: 700 million
- Crashed duration: 6 days
- Crashed cost: 0 million (not given, assume it is 0 for calculation)
[tex]\[ \text{Crashing cost per day for B} = \frac{0 - 700}{7 - 6} = \frac{-700}{1} = -700 \text{ million per day} \][/tex]
3. Activity C:
- Normal duration: 3 days
- Normal cost: 0 million (not given, assume it is 0 for calculation)
- Crashed duration: None (not given, assume it is same as normal duration)
[tex]\[ \text{Crashing cost per day for C} = 0 \text{ million per day} \][/tex]
4. Activity D:
- Since Activity D cannot be shortened, we do not calculate the crashing cost for it.
5. Activity E:
- Normal duration: 9 days
- Normal cost: 3750 million
- Crashed duration: 6 days
- Crashed cost: 9000 million
[tex]\[ \text{Crashing cost per day for E} = \frac{9000 - 3750}{9 - 6} = \frac{5250}{3} = 1750 \text{ million per day} \][/tex]
6. Activity F:
- Normal duration: 4 days
- Normal cost: 0 million (not given, assume it is 0 for calculation)
- Crashed duration: None (not given, assume it is same as normal duration)
[tex]\[ \text{Crashing cost per day for F} = 0 \text{ million per day} \][/tex]
7. Activity G:
- Normal duration: None (not given, assume it is same as crashed duration)
- Normal cost: 1600 million
- Crashed duration: 3 days
- Crashed cost: 2500 million
[tex]\[ \text{Crashing cost per day for G} = 0 \text{ million per day} \][/tex]
8. Activity H:
- Normal duration: 8 days
- Normal cost: 9000 million
- Crashed duration: 5 days
- Crashed cost: 15000 million
[tex]\[ \text{Crashing cost per day for H} = \frac{15000 - 9000}{8 - 5} = \frac{6000}{3} = 2000 \text{ million per day} \][/tex]
### Summary of Crashing Costs per Day for Each Activity:
- Activity A: 700 million per day
- Activity B: -700 million per day
- Activity C: 0 million per day
- Activity D: Not applicable (cannot be shortened)
- Activity E: 1750 million per day
- Activity F: 0 million per day
- Activity G: 0 million per day
- Activity H: 2000 million per day
Thus, these are the crashing costs for each activity in the project.
Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Discover more at Westonci.ca. Return for the latest expert answers and updates on various topics.