Welcome to Westonci.ca, your one-stop destination for finding answers to all your questions. Join our expert community now! Our Q&A platform provides quick and trustworthy answers to your questions from experienced professionals in different areas of expertise. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.

Geoffrey contracted to make a dress for Sylvia. Per the terms of the contract, Geoffrey was supposed to make the dress out of a specific type of silk and to complete the dress by December 4th so Sylvia could wear the dress to an event the night of December 5th. The silk took longer than expected to arrive and did not arrive until December 6th. Sylvia sued Geoffrey for breach of contract. Can she win?

a. No, because Geoffrey was not at fault for the silk being late.
b. No, because the arrival of the silk was a condition.
c. Yes, because Sylvia needed the dress on December 5th.
d. Yes, because Geoffrey should have made the dresses out of other material.

Sagot :

Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. We appreciate your time. Please revisit us for more reliable answers to any questions you may have. Keep exploring Westonci.ca for more insightful answers to your questions. We're here to help.