Welcome to Westonci.ca, the place where your questions find answers from a community of knowledgeable experts. Explore thousands of questions and answers from a knowledgeable community of experts on our user-friendly platform. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.
Sagot :
To determine the project's Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF), slack for each activity, the total project completion time, and the critical path, follow these steps:
### Activity Data
Based on the given activity data:
[tex]\[ \begin{array}{|c|c|c|} \hline \text{Activity} & \text{Time (weeks)} & \text{Predecessors} \\ \hline A & 6 & - \\ B & 6 & - \\ C & 3 & A \\ D & 3 & A \\ E & 4 & B \\ F & 7 & B \\ G & 9 & C, E \\ H & 8 & D, F \\ \hline \end{array} \][/tex]
### Early Start (ES) and Early Finish (EF)
The ES and EF for each activity are calculated as follows:
[tex]\[ \begin{array}{|c|c|c|} \hline \text{Activity} & \text{ES} & \text{EF} \\ \hline A & 0 & 6 \\ B & 0 & 6 \\ C & 6 & 9 \\ D & 6 & 9 \\ E & 6 & 10 \\ F & 6 & 13 \\ G & 10 & 19 \\ H & 13 & 21 \\ \hline \end{array} \][/tex]
### Late Start (LS) and Late Finish (LF)
The LS and LF for each activity are calculated as follows:
[tex]\[ \begin{array}{|c|c|c|} \hline \text{Activity} & \text{LS} & \text{LF} \\ \hline A & 0 & 6 \\ B & 0 & 6 \\ C & 6 & 9 \\ D & 6 & 9 \\ E & 6 & 10 \\ F & 6 & 13 \\ G & 10 & 19 \\ H & 13 & 21 \\ \hline \end{array} \][/tex]
### Slack Calculation
The slack (or float) for each activity is calculated as:
[tex]\[ \text{Slack} = \text{LS} - \text{ES} = \text{LF} - \text{EF} \][/tex]
Using the given LS and ES values:
[tex]\[ \begin{array}{|c|c|} \hline \text{Activity} & \text{Slack} \\ \hline A & 0 \\ B & 0 \\ C & 0 \\ D & 0 \\ E & 0 \\ F & 0 \\ G & 0 \\ H & 0 \\ \hline \end{array} \][/tex]
### Total Project Completion Time
The total project completion time is the EF of the last activity in the critical path, which is 21 weeks.
### Critical Path
An activity is part of the critical path if it has zero slack (Slack = 0). Therefore, the activities in the critical path are:
[tex]\[ [A, B, C, D, E, F, G, H] \][/tex]
### Summary
- Slack for each activity:
[tex]\[ \begin{array}{|c|c|} \hline \text{Activity} & \text{Slack} \\ \hline A & 0 \\ B & 0 \\ C & 0 \\ D & 0 \\ E & 0 \\ F & 0 \\ G & 0 \\ H & 0 \\ \hline \end{array} \][/tex]
- Total project completion time: 21 weeks
- Critical path: [tex]\[ [A, B, C, D, E, F, G, H] \][/tex]
### Activity Data
Based on the given activity data:
[tex]\[ \begin{array}{|c|c|c|} \hline \text{Activity} & \text{Time (weeks)} & \text{Predecessors} \\ \hline A & 6 & - \\ B & 6 & - \\ C & 3 & A \\ D & 3 & A \\ E & 4 & B \\ F & 7 & B \\ G & 9 & C, E \\ H & 8 & D, F \\ \hline \end{array} \][/tex]
### Early Start (ES) and Early Finish (EF)
The ES and EF for each activity are calculated as follows:
[tex]\[ \begin{array}{|c|c|c|} \hline \text{Activity} & \text{ES} & \text{EF} \\ \hline A & 0 & 6 \\ B & 0 & 6 \\ C & 6 & 9 \\ D & 6 & 9 \\ E & 6 & 10 \\ F & 6 & 13 \\ G & 10 & 19 \\ H & 13 & 21 \\ \hline \end{array} \][/tex]
### Late Start (LS) and Late Finish (LF)
The LS and LF for each activity are calculated as follows:
[tex]\[ \begin{array}{|c|c|c|} \hline \text{Activity} & \text{LS} & \text{LF} \\ \hline A & 0 & 6 \\ B & 0 & 6 \\ C & 6 & 9 \\ D & 6 & 9 \\ E & 6 & 10 \\ F & 6 & 13 \\ G & 10 & 19 \\ H & 13 & 21 \\ \hline \end{array} \][/tex]
### Slack Calculation
The slack (or float) for each activity is calculated as:
[tex]\[ \text{Slack} = \text{LS} - \text{ES} = \text{LF} - \text{EF} \][/tex]
Using the given LS and ES values:
[tex]\[ \begin{array}{|c|c|} \hline \text{Activity} & \text{Slack} \\ \hline A & 0 \\ B & 0 \\ C & 0 \\ D & 0 \\ E & 0 \\ F & 0 \\ G & 0 \\ H & 0 \\ \hline \end{array} \][/tex]
### Total Project Completion Time
The total project completion time is the EF of the last activity in the critical path, which is 21 weeks.
### Critical Path
An activity is part of the critical path if it has zero slack (Slack = 0). Therefore, the activities in the critical path are:
[tex]\[ [A, B, C, D, E, F, G, H] \][/tex]
### Summary
- Slack for each activity:
[tex]\[ \begin{array}{|c|c|} \hline \text{Activity} & \text{Slack} \\ \hline A & 0 \\ B & 0 \\ C & 0 \\ D & 0 \\ E & 0 \\ F & 0 \\ G & 0 \\ H & 0 \\ \hline \end{array} \][/tex]
- Total project completion time: 21 weeks
- Critical path: [tex]\[ [A, B, C, D, E, F, G, H] \][/tex]
Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. Get the answers you need at Westonci.ca. Stay informed by returning for our latest expert advice.