Looking for answers? Westonci.ca is your go-to Q&A platform, offering quick, trustworthy responses from a community of experts. Get immediate and reliable answers to your questions from a community of experienced experts on our platform. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.

Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels.

\begin{tabular}{|c|c|c|c|c|c|c|c|c|c|}
\hline
\multirow[b]{2}{}{Activity} & \multicolumn{3}{|c|}{Time (weeks)} & \multirow{2}{}{\begin{tabular}{l}Immediate\\Predecessor(s)\end{tabular}} & \multirow[b]{2}{}{Activity} & \multicolumn{3}{|c|}{Time (weeks)} & \multirow{2}{}{\begin{tabular}{l}Immediate\\Predecessor(s)\end{tabular}} \\
\hline
& [tex]$a$[/tex] & [tex]$m$[/tex] & [tex]$b$[/tex] & & & [tex]$a$[/tex] & [tex]$m$[/tex] & [tex]$b$[/tex] & \\
\hline
[tex]$\bar{A}$[/tex] & 4 & 9 & 10 & - & [tex]$G$[/tex] & 3 & 3 & 4 & [tex]$\overline{C, E}$[/tex] \\
\hline
[tex]$B$[/tex] & 2 & 9 & 24 & [tex]$A$[/tex] & [tex]$H$[/tex] & 2 & 2 & 2 & [tex]$F$[/tex] \\
\hline
[tex]$C$[/tex] & 9 & 12 & 18 & [tex]$A$[/tex] & [tex]$I$[/tex] & 5 & 5 & 5 & [tex]$F$[/tex] \\
\hline
[tex]$D$[/tex] & 4 & 7 & 10 & [tex]$A$[/tex] & [tex]$J$[/tex] & 6 & 7 & 14 & [tex]$D, G, H$[/tex] \\
\hline
[tex]$E$[/tex] & 1 & 3 & 4 & [tex]$B$[/tex] & [tex]$K$[/tex] & 1 & 1 & 4 & [tex]$I, J$[/tex] \\
\hline
[tex]$F$[/tex] & 5 & 8 & 20 & [tex]$\overline{C, E}$[/tex] & & & & & \\
\hline
\end{tabular}

a) The expected (estimated) time for activity [tex]$C$[/tex] is [tex]$\square$[/tex] weeks. (Round your response to two decimal places.)


Sagot :

To find the expected (estimated) time for activity \( C \), we use the PERT (Program Evaluation and Review Technique) formula for the expected time:

[tex]\[ TE = \frac{a + 4m + b}{6} \][/tex]

where
- \( a \) is the optimistic time,
- \( m \) is the most likely time, and
- \( b \) is the pessimistic time for the activity.

For activity \( C \), the given times are:
- \( a = 9 \) weeks (optimistic time),
- \( m = 12 \) weeks (most likely time),
- \( b = 18 \) weeks (pessimistic time).

Plugging these values into the PERT formula, we get:

[tex]\[ TE = \frac{9 + 4(12) + 18}{6} \][/tex]

First, calculate the values inside the parentheses:

[tex]\[ 9 + 4(12) + 18 = 9 + 48 + 18 = 75 \][/tex]

Next, divide the sum by 6:

[tex]\[ TE = \frac{75}{6} \approx 12.5 \][/tex]

Hence, the expected (estimated) time for activity [tex]\( C \)[/tex] is [tex]\( 12.5 \)[/tex] weeks.
Thank you for visiting our platform. We hope you found the answers you were looking for. Come back anytime you need more information. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Keep exploring Westonci.ca for more insightful answers to your questions. We're here to help.