Welcome to Westonci.ca, where curiosity meets expertise. Ask any question and receive fast, accurate answers from our knowledgeable community. Join our Q&A platform and get accurate answers to all your questions from professionals across multiple disciplines. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.

Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels.

\begin{tabular}{|c|c|c|c|c|c|c|c|c|c|}
\hline
\multirow[b]{2}{}{Activity} & \multicolumn{3}{|c|}{Time (weeks)} & \multirow{2}{}{\begin{tabular}{l} Immediate \\ Predecessor(s) \end{tabular}} & \multirow[b]{2}{}{Activity} & \multicolumn{3}{|c|}{Time (weeks)} & \multirow{2}{}{\begin{tabular}{l} Immediate \\ Predecessor(s) \end{tabular}} \\
\hline
& a & [tex]$m$[/tex] & [tex]$b$[/tex] & & & a & [tex]$m$[/tex] & [tex]$b$[/tex] & \\
\hline
A & 4 & 9 & 10 & - & G & 3 & 3 & 4 & [tex]$\overline{C, E}$[/tex] \\
\hline
B & 2 & 9 & 24 & A & H & 2 & 2 & 2 & F \\
\hline
C & 9 & 12 & 18 & A & I & 5 & 5 & 5 & F \\
\hline
D & 4 & 7 & 10 & A & J & 6 & 7 & 14 & D, G, H \\
\hline
E & 1 & 3 & 4 & B & K & 1 & 1 & 4 & I, J \\
\hline
F & 5 & 8 & 20 & C, E & & & & & \\
\hline
\end{tabular}

a) The expected (estimated) time for activity [tex]$C$[/tex] is 12.5 weeks. (Round your response to two decimal places.)

b) The variance for activity [tex]$C$[/tex] is [tex]$\square$[/tex] weeks. (Round your response to two decimal places.)


Sagot :

To solve this problem using the PERT (Program Evaluation Review Technique) formulas, let's find the expected time and the variance for activity \( C \).

### Step-by-Step Solution

a) Expected (estimated) time \( t_e \) for activity \( C \)

The PERT formula for expected time \( t_e \) is:
[tex]\[ t_e = \frac{a + 4m + b}{6} \][/tex]

Given:
- Optimistic time (\( a \)) = 9 weeks
- Most likely time (\( m \)) = 12 weeks
- Pessimistic time (\( b \)) = 18 weeks

Substitute the values into the formula:
[tex]\[ t_e = \frac{9 + 4(12) + 18}{6} \][/tex]

Calculate inside the parentheses first:
[tex]\[ t_e = \frac{9 + 48 + 18}{6} \][/tex]
[tex]\[ t_e = \frac{75}{6} \approx 12.5 \][/tex]

So, the expected (estimated) time for activity \( C \) is 12.5 weeks.

b) Variance for activity \( C \)

The PERT formula for the variance \( \sigma^2 \) is:
[tex]\[ \text{Variance} = \left( \frac{b - a}{6} \right)^2 \][/tex]

Given:
- Optimistic time (\( a \)) = 9 weeks
- Pessimistic time (\( b \)) = 18 weeks

Substitute the values into the formula:
[tex]\[ \text{Variance} = \left( \frac{18 - 9}{6} \right)^2 \][/tex]

Calculate inside the parentheses first:
[tex]\[ \text{Variance} = \left( \frac{9}{6} \right)^2 \][/tex]
[tex]\[ \text{Variance} = \left( 1.5 \right)^2 \][/tex]
[tex]\[ \text{Variance} = 2.25 \][/tex]

So, the variance for activity [tex]\( C \)[/tex] is 2.25 weeks.