Get the answers you need at Westonci.ca, where our expert community is always ready to help with accurate information. Join our platform to connect with experts ready to provide precise answers to your questions in various areas. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.
Sagot :
To find the probability that Hopkins Hospitality will finish the project in 42 weeks or less, we need to follow a systematic approach using the given parameters and some statistical calculations outlined below.
First, we highlight the given data:
- Estimated time \(T_{CP}\) for the critical path is 42.5 weeks.
- Variance \(\sigma^2_{CP}\) along the critical path is 22.97 weeks.
- Target project completion time \(T\) is 42 weeks.
### Step-by-step Solution:
1. Calculate the Standard Deviation (\(\sigma_{CP}\)) of the Project Time:
The standard deviation is the square root of the variance. This helps in understanding the spread of the possible completion times around the mean.
[tex]\[ \sigma_{CP} = \sqrt{\sigma^2_{CP}} = \sqrt{22.97} \approx 4.793 \text{ weeks} \quad (\text{rounded to three decimal places}) \][/tex]
2. Calculate the Z-score:
The Z-score is a measure that describes how many standard deviations a particular value is from the mean. It is calculated as:
[tex]\[ Z = \frac{T - T_{CP}}{\sigma_{CP}} \][/tex]
Substituting the given values, we get:
[tex]\[ Z = \frac{42 - 42.5}{4.793} \approx -0.104 \quad (\text{rounded to three decimal places}) \][/tex]
3. Determine the Probability:
The probability that the project will complete in 42 weeks or less can be found using the Cumulative Distribution Function (CDF) for the normal distribution at the computed Z-score.
Using a standard normal distribution table or a computational tool, we find the cumulative probability corresponding to the Z-score of -0.104.
[tex]\[ P(Z < -0.104) \approx 0.458 \quad (\text{rounded to three decimal places}) \][/tex]
### Conclusion:
The probability that Hopkins Hospitality will finish the project in 42 weeks or less is approximately:
[tex]\[ \boxed{0.458} \][/tex]
First, we highlight the given data:
- Estimated time \(T_{CP}\) for the critical path is 42.5 weeks.
- Variance \(\sigma^2_{CP}\) along the critical path is 22.97 weeks.
- Target project completion time \(T\) is 42 weeks.
### Step-by-step Solution:
1. Calculate the Standard Deviation (\(\sigma_{CP}\)) of the Project Time:
The standard deviation is the square root of the variance. This helps in understanding the spread of the possible completion times around the mean.
[tex]\[ \sigma_{CP} = \sqrt{\sigma^2_{CP}} = \sqrt{22.97} \approx 4.793 \text{ weeks} \quad (\text{rounded to three decimal places}) \][/tex]
2. Calculate the Z-score:
The Z-score is a measure that describes how many standard deviations a particular value is from the mean. It is calculated as:
[tex]\[ Z = \frac{T - T_{CP}}{\sigma_{CP}} \][/tex]
Substituting the given values, we get:
[tex]\[ Z = \frac{42 - 42.5}{4.793} \approx -0.104 \quad (\text{rounded to three decimal places}) \][/tex]
3. Determine the Probability:
The probability that the project will complete in 42 weeks or less can be found using the Cumulative Distribution Function (CDF) for the normal distribution at the computed Z-score.
Using a standard normal distribution table or a computational tool, we find the cumulative probability corresponding to the Z-score of -0.104.
[tex]\[ P(Z < -0.104) \approx 0.458 \quad (\text{rounded to three decimal places}) \][/tex]
### Conclusion:
The probability that Hopkins Hospitality will finish the project in 42 weeks or less is approximately:
[tex]\[ \boxed{0.458} \][/tex]
We hope this information was helpful. Feel free to return anytime for more answers to your questions and concerns. Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. Thank you for visiting Westonci.ca, your go-to source for reliable answers. Come back soon for more expert insights.