Looking for reliable answers? Westonci.ca is the ultimate Q&A platform where experts share their knowledge on various topics. Join our platform to connect with experts ready to provide precise answers to your questions in different areas. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.

Greenwood Company manufacturers two products- 14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as s whole and for products Y and Z:
Machining. Machine-hours. $198,000. 10,000MHs
Machine setups. Number of setups. $86,400. 180 setups
Production design. Number of Products. $82,000. 2 products
General factory. Direct labor-hours. $248,000. 10,000 DLHs

Activity measure. Product Y. Product Z
Machining. 7,800. 2,200
Number of setups. 50. 130
Number of Products. 1. 1
Direct labor-hours. 7,800. 2,200

What is the activity rate for the machining activity cost pool? (Round your answer to 2 decimal places.)
Activity rate _____ per MH