Westonci.ca is the best place to get answers to your questions, provided by a community of experienced and knowledgeable experts. Connect with a community of experts ready to help you find solutions to your questions quickly and accurately. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.
Sagot :
Answer:
3.5 days
Step-by-step explanation:
You want to know the number of days until work is completed if P works every day and Q and R work on alternate days, given P, Q, R can finish the work individually in 5, 10, and 15 days, respectively.
Daily work
When each works alone, the amount of work completed in one day is ...
P: 1/5
Q: 1/10
R: 1/15
On odd days, when P and Q work together, the amount of work completed is ...
(1/5) +(1/10) = 3/10
On even days, when P and R work together, the amount of work completed is ...
(1/5) +(1/15) = 4/15
Estimate
Both of these values are less than 1/3, so we know it will take at least 3 days to complete the work. In 3 days, the work completed is ...
3/10 + 4/15 + 3/10 = 13/15 . . . . . . . . of the job
So, after 3 days, the amount of work remaining is ...
1 -13/15 = 2/15
On the 4th day, the work is completed at the rate of 4/15 job per day, so the fraction of the day required to finish up is ...
[tex]\dfrac{\text{remaining work}}{\text{work per day}}=\dfrac{2/15}{4/15}\text{ day}=\dfrac{2}{4}\text{ day}=\dfrac{1}{2}\text{ day}[/tex]
The work can be completed in 3 1/2 days using the given schedule.
We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. We're glad you chose Westonci.ca. Revisit us for updated answers from our knowledgeable team.