Westonci.ca makes finding answers easy, with a community of experts ready to provide you with the information you seek. Join our platform to connect with experts ready to provide precise answers to your questions in various areas. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.
Sagot :
Answer:
3.5 days
Step-by-step explanation:
You want to know the number of days until work is completed if P works every day and Q and R work on alternate days, given P, Q, R can finish the work individually in 5, 10, and 15 days, respectively.
Daily work
When each works alone, the amount of work completed in one day is ...
P: 1/5
Q: 1/10
R: 1/15
On odd days, when P and Q work together, the amount of work completed is ...
(1/5) +(1/10) = 3/10
On even days, when P and R work together, the amount of work completed is ...
(1/5) +(1/15) = 4/15
Estimate
Both of these values are less than 1/3, so we know it will take at least 3 days to complete the work. In 3 days, the work completed is ...
3/10 + 4/15 + 3/10 = 13/15 . . . . . . . . of the job
So, after 3 days, the amount of work remaining is ...
1 -13/15 = 2/15
On the 4th day, the work is completed at the rate of 4/15 job per day, so the fraction of the day required to finish up is ...
[tex]\dfrac{\text{remaining work}}{\text{work per day}}=\dfrac{2/15}{4/15}\text{ day}=\dfrac{2}{4}\text{ day}=\dfrac{1}{2}\text{ day}[/tex]
The work can be completed in 3 1/2 days using the given schedule.
Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Get the answers you need at Westonci.ca. Stay informed with our latest expert advice.