Westonci.ca is the Q&A platform that connects you with experts who provide accurate and detailed answers. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.

An approved change was implemented to manage a risk. Three months later, the project manager finds that the change did not yield the desired result. In fact, the change led to adverse consequences.
What should the project manager do to avoid this issue in the future? Select one.

A. Review the assumption log to revisit or change current assumptions.
B. Confirm that an implemented risk response is effective.
C. Update the risk information to the lessons learned register.
D. Evaluate new risks and update the probability and impact matrix.

Sagot :

Thank you for your visit. We are dedicated to helping you find the information you need, whenever you need it. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. Thank you for using Westonci.ca. Come back for more in-depth answers to all your queries.