Welcome to Westonci.ca, where curiosity meets expertise. Ask any question and receive fast, accurate answers from our knowledgeable community. Get the answers you need quickly and accurately from a dedicated community of experts on our Q&A platform. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.

An approved change was implemented to manage a risk. Three months later, the project manager finds that the change did not yield the desired result. In fact, the change led to adverse consequences.
What should the project manager do to avoid this issue in the future? Select one.

A. Review the assumption log to revisit or change current assumptions.
B. Confirm that an implemented risk response is effective.
C. Update the risk information to the lessons learned register.
D. Evaluate new risks and update the probability and impact matrix.