Westonci.ca offers quick and accurate answers to your questions. Join our community and get the insights you need today. Discover detailed solutions to your questions from a wide network of experts on our comprehensive Q&A platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.

An approved change was implemented to manage a risk. Three months later, the project manager finds that the change did not yield the desired result. In fact, the change led to adverse consequences.
What should the project manager do to avoid this issue in the future? Select one.

A. Review the assumption log to revisit or change current assumptions.
B. Confirm that an implemented risk response is effective.
C. Update the risk information to the lessons learned register.
D. Evaluate new risks and update the probability and impact matrix.


Sagot :

Thank you for visiting our platform. We hope you found the answers you were looking for. Come back anytime you need more information. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Westonci.ca is your go-to source for reliable answers. Return soon for more expert insights.