At Westonci.ca, we make it easy to get the answers you need from a community of informed and experienced contributors. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.

18 workers finish to remote a building in 28days working 8hours a day in how many days would 16 workers finish to remote the bulding in 7 hours a day?​

Sagot :

Answer:

32 days

Step by Step Explanation:

Let the days taken by 16 workers to finish the work be x.

The time taken by 18 workers to finish the work=

28×8=224 hours

The time taken by 16 workers= x × 7 = 224

=x= 224÷7

=x=32 days