At Westonci.ca, we provide clear, reliable answers to all your questions. Join our vibrant community and get the solutions you need. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.

Part 2 of 6
Points: 0.38 of 1

Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new infrastructure.

\begin{tabular}{crrrc|ccccc}
\hline & \multicolumn{3}{c}{ Time (weeks) } & Immediate & & \multicolumn{3}{c}{ Time (weeks) } & Immediate \\
\cline { 2 - 8 } Activity & [tex]$a$[/tex] & [tex]$m$[/tex] & [tex]$b$[/tex] & Predecessor(s) & Activity & [tex]$a$[/tex] & [tex]$m$[/tex] & [tex]$b$[/tex] & Predecessor(s) \\
\hline A & 6 & 9 & 12 & - & G & 3 & 3 & 5 & C, E \\
B & 1 & 8 & 24 & A & H & 2 & 2 & 2 & F \\
C & 9 & 14 & 18 & A & I & 5 & 5 & 5 & F \\
D & 5 & 7 & 10 & A & J & 6 & 8 & 14 & D, G, H \\
E & 1 & 3 & 4 & B & K & 1 & 1 & 4 & I, J \\
F & 5 & 8 & 20 & C, E & & & & & \\
\hline
\end{tabular}

a) The expected (estimated) time for activity [tex]$C$[/tex] is 13.83 weeks. (Round your response to two decimal places.)

b) The variance for activity [tex]$C$[/tex] is [tex]$\square$[/tex] weeks. (Round your response to two decimal places.)


Sagot :

To determine the variance for activity [tex]\(C\)[/tex], we can use the formula for variance in the Program Evaluation and Review Technique (PERT), which is given by:

[tex]\[ \text{Variance} = \left(\frac{b - a}{6}\right)^2 \][/tex]

where:
- [tex]\(a\)[/tex] is the optimistic time estimate,
- [tex]\(m\)[/tex] is the most likely time estimate,
- [tex]\(b\)[/tex] is the pessimistic time estimate.

Given the times for activity [tex]\(C\)[/tex]:
- [tex]\(a = 9\)[/tex] weeks,
- [tex]\(m = 14\)[/tex] weeks,
- [tex]\(b = 18\)[/tex] weeks,

we can substitute these values into the variance formula.

First, calculate [tex]\( \frac{b - a}{6} \)[/tex]:
[tex]\[ \frac{18 - 9}{6} = \frac{9}{6} = 1.5 \][/tex]

Next, square the result to find the variance:
[tex]\[ (1.5)^2 = 2.25 \][/tex]

Therefore, the variance for activity [tex]\(C\)[/tex] is [tex]\(2.25\)[/tex] weeks.
We hope our answers were helpful. Return anytime for more information and answers to any other questions you may have. We hope this was helpful. Please come back whenever you need more information or answers to your queries. Thank you for trusting Westonci.ca. Don't forget to revisit us for more accurate and insightful answers.