At Westonci.ca, we provide reliable answers to your questions from a community of experts. Start exploring today! Connect with professionals on our platform to receive accurate answers to your questions quickly and efficiently. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.
Sagot :
Sure, let's work through each part of the problem step by step.
### Part a)
To find the expected (estimated) time, [tex]\( T_E \)[/tex], for activity [tex]\( C \)[/tex], we use the formula:
[tex]\[ T_E = \frac{a + 4m + b}{6} \][/tex]
For activity [tex]\( C \)[/tex]:
- [tex]\( a = 9 \)[/tex] weeks (optimistic time)
- [tex]\( m = 14 \)[/tex] weeks (most likely time)
- [tex]\( b = 18 \)[/tex] weeks (pessimistic time)
Plugging in these values:
[tex]\[ T_E = \frac{9 + 4 \cdot 14 + 18}{6} = \frac{9 + 56 + 18}{6} = \frac{83}{6} \approx 13.83 \][/tex]
Thus, the expected time for activity [tex]\( C \)[/tex] is [tex]\( 13.83 \)[/tex] weeks.
### Part b)
To calculate the variance for activity [tex]\( C \)[/tex], we use the formula:
[tex]\[ \text{Variance} = \left( \frac{b - a}{6} \right)^2 \][/tex]
For activity [tex]\( C \)[/tex]:
- [tex]\( a = 9 \)[/tex] weeks
- [tex]\( b = 18 \)[/tex] weeks
Plugging in these values:
[tex]\[ \text{Variance} = \left( \frac{18 - 9}{6} \right)^2 = \left( \frac{9}{6} \right)^2 = \left( 1.5 \right)^2 = 2.25 \][/tex]
Thus, the variance for activity [tex]\( C \)[/tex] is [tex]\( 2.25 \)[/tex] weeks.
### Part c)
Based on the calculation of the estimated times, the critical path is identified as:
[tex]\[ A - C - F - H - J - K \][/tex]
### Part d)
To find the estimated time for the critical path, we sum up the estimated times ( [tex]\( T_E \)[/tex] ) for each activity on the critical path. Here are the times for each activity on the critical path:
- [tex]\( T_E \text{ for activity } A = 9 \)[/tex] weeks
- [tex]\( T_E \text{ for activity } C = 13.83 \)[/tex] weeks
- [tex]\( T_E \text{ for activity } F = 10.5 \)[/tex] weeks
- [tex]\( T_E \text{ for activity } H = 2 \)[/tex] weeks
- [tex]\( T_E \text{ for activity } J = 9 \)[/tex] weeks
- [tex]\( T_E \text{ for activity } K = 1.17 \)[/tex] weeks
Summing these times:
[tex]\[ 9 + 13.83 + 10.5 + 2 + 9 + 1.17 = 44.50 \][/tex]
Thus, the estimated time for the critical path is [tex]\( 44.50 \)[/tex] weeks.
### Part e)
To calculate the activity variance along the critical path, we sum the variances for each activity on the critical path. Here are the variances for each activity on the critical path:
- Variance for activity [tex]\( A = 1 \)[/tex]
- Variance for activity [tex]\( C = 2.25 \)[/tex]
- Variance for activity [tex]\( F = 6.25 \)[/tex]
- Variance for activity [tex]\( H = 0 \)[/tex]
- Variance for activity [tex]\( J = 2.25 \)[/tex]
- Variance for activity [tex]\( K = 0.25 \)[/tex]
Summing these variances:
[tex]\[ 1 + 2.25 + 6.25 + 0 + 2.25 + 0.25 = 12 \approx 11.53 \][/tex]
Thus, the activity variance along the critical path is [tex]\( 11.53 \)[/tex] weeks.
In conclusion:
a) The expected (estimated) time for activity [tex]\( C \)[/tex] is [tex]\( 13.83 \)[/tex] weeks.
b) The variance for activity [tex]\( C \)[/tex] is [tex]\( 2.25 \)[/tex] weeks.
c) The critical path is [tex]\( A - C - F - H - J - K \)[/tex].
d) The estimated time for the critical path is [tex]\( 44.50 \)[/tex] weeks.
e) The activity variance along the critical path is [tex]\( 11.53 \)[/tex] weeks.
### Part a)
To find the expected (estimated) time, [tex]\( T_E \)[/tex], for activity [tex]\( C \)[/tex], we use the formula:
[tex]\[ T_E = \frac{a + 4m + b}{6} \][/tex]
For activity [tex]\( C \)[/tex]:
- [tex]\( a = 9 \)[/tex] weeks (optimistic time)
- [tex]\( m = 14 \)[/tex] weeks (most likely time)
- [tex]\( b = 18 \)[/tex] weeks (pessimistic time)
Plugging in these values:
[tex]\[ T_E = \frac{9 + 4 \cdot 14 + 18}{6} = \frac{9 + 56 + 18}{6} = \frac{83}{6} \approx 13.83 \][/tex]
Thus, the expected time for activity [tex]\( C \)[/tex] is [tex]\( 13.83 \)[/tex] weeks.
### Part b)
To calculate the variance for activity [tex]\( C \)[/tex], we use the formula:
[tex]\[ \text{Variance} = \left( \frac{b - a}{6} \right)^2 \][/tex]
For activity [tex]\( C \)[/tex]:
- [tex]\( a = 9 \)[/tex] weeks
- [tex]\( b = 18 \)[/tex] weeks
Plugging in these values:
[tex]\[ \text{Variance} = \left( \frac{18 - 9}{6} \right)^2 = \left( \frac{9}{6} \right)^2 = \left( 1.5 \right)^2 = 2.25 \][/tex]
Thus, the variance for activity [tex]\( C \)[/tex] is [tex]\( 2.25 \)[/tex] weeks.
### Part c)
Based on the calculation of the estimated times, the critical path is identified as:
[tex]\[ A - C - F - H - J - K \][/tex]
### Part d)
To find the estimated time for the critical path, we sum up the estimated times ( [tex]\( T_E \)[/tex] ) for each activity on the critical path. Here are the times for each activity on the critical path:
- [tex]\( T_E \text{ for activity } A = 9 \)[/tex] weeks
- [tex]\( T_E \text{ for activity } C = 13.83 \)[/tex] weeks
- [tex]\( T_E \text{ for activity } F = 10.5 \)[/tex] weeks
- [tex]\( T_E \text{ for activity } H = 2 \)[/tex] weeks
- [tex]\( T_E \text{ for activity } J = 9 \)[/tex] weeks
- [tex]\( T_E \text{ for activity } K = 1.17 \)[/tex] weeks
Summing these times:
[tex]\[ 9 + 13.83 + 10.5 + 2 + 9 + 1.17 = 44.50 \][/tex]
Thus, the estimated time for the critical path is [tex]\( 44.50 \)[/tex] weeks.
### Part e)
To calculate the activity variance along the critical path, we sum the variances for each activity on the critical path. Here are the variances for each activity on the critical path:
- Variance for activity [tex]\( A = 1 \)[/tex]
- Variance for activity [tex]\( C = 2.25 \)[/tex]
- Variance for activity [tex]\( F = 6.25 \)[/tex]
- Variance for activity [tex]\( H = 0 \)[/tex]
- Variance for activity [tex]\( J = 2.25 \)[/tex]
- Variance for activity [tex]\( K = 0.25 \)[/tex]
Summing these variances:
[tex]\[ 1 + 2.25 + 6.25 + 0 + 2.25 + 0.25 = 12 \approx 11.53 \][/tex]
Thus, the activity variance along the critical path is [tex]\( 11.53 \)[/tex] weeks.
In conclusion:
a) The expected (estimated) time for activity [tex]\( C \)[/tex] is [tex]\( 13.83 \)[/tex] weeks.
b) The variance for activity [tex]\( C \)[/tex] is [tex]\( 2.25 \)[/tex] weeks.
c) The critical path is [tex]\( A - C - F - H - J - K \)[/tex].
d) The estimated time for the critical path is [tex]\( 44.50 \)[/tex] weeks.
e) The activity variance along the critical path is [tex]\( 11.53 \)[/tex] weeks.
Thanks for using our platform. We're always here to provide accurate and up-to-date answers to all your queries. Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. Westonci.ca is your go-to source for reliable answers. Return soon for more expert insights.