Welcome to Westonci.ca, the place where your questions find answers from a community of knowledgeable experts. Our platform provides a seamless experience for finding precise answers from a network of experienced professionals. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform.

A project team is small and the team members have known each other for a long time. The team’s project is in the execution phase. Recently, a team member told the new project manager that another team member has been complaining about how the project is being managed. How should this new project manager respond?

O Preview the current stakeholder engagement plan for the way to resolve the difficulty.
O Schedule a mandatory team meeting which will lead to the creation of a new social contract.
O Notify team members that they should submit anonymous recommendations for a new social contract.
O Send a survey to team members, requesting suggestions for dealing with the dissatisfaction.