Welcome to Westonci.ca, where your questions are met with accurate answers from a community of experts and enthusiasts. Connect with a community of experts ready to help you find accurate solutions to your questions quickly and efficiently. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.

\begin{tabular}{|l|l|l|l|l|l|l|l|}
\hline Activity & A & B & C & D & E & F & G \\
\hline Duration & 3 & 5 & 4 & 10 & 7 & 14 & 6 \\
\hline Predecessor & - & - & A & B,C & A,G & D,E & - \\
\hline
\end{tabular}

Tasks:
1. Construct the network diagram.
2. Indicate the critical path.
3. Determine the project duration.


Sagot :

Sure! Let's work through the steps to construct the network diagram, indicate the critical path, and determine the project duration. Here's the problem broken down into its components:

### 1. Construct the Network Diagram:
To construct a network diagram, we need to represent each activity and its dependencies.

- Activity A has no predecessors.
- Activity B has no predecessors.
- Activity C depends on A.
- Activity D depends on B and C.
- Activity E depends on A and G.
- Activity F depends on D and E.
- Activity G has no predecessors.

We'll connect each activity to its successors to show the dependencies:

```
Start --> A --> C --> D --> F --> End
| |
|--> E --> F --|
|
B --> D --> F
|
G --> E --> F
```

### 2. Indicate the Critical Path:
The critical path is the longest path through the network diagram. We need to find all paths and calculate their durations.
Here's the process:
- Identify all possible paths from start to finish.
- Calculate the total duration of each path.
- The path with the longest duration is the critical path.

Considering the dependencies, potential paths could be:
1. Start -> A -> C -> D -> F -> End
2. Start -> B -> D -> F -> End
3. Start -> A -> E -> F -> End
4. Start -> G -> E -> F -> End

Next, we calculate the duration for each path:

1. Start -> A -> C -> D -> F -> End:
- A (3) + C (4) + D (10) + F (14) = 31

2. Start -> B -> D -> F -> End:
- B (5) + D (10) + F (14) = 29

3. Start -> A -> E -> F -> End:
- A (3) + E (7) + F (14) = 24

4. Start -> G -> E -> F -> End:
- G (6) + E (7) + F (14) = 27

Now we compare the durations:
- Path 1: 31
- Path 2: 29
- Path 3: 24
- Path 4: 27

The longest duration is 31, so the critical path is:

A -> C -> D -> F

### 3. Determine the Project Duration:
The duration of the project is the total duration of the critical path.

The project duration is 31 units of time.

### Summary:
- The critical path is A -> C -> D -> F.
- The project duration is 31 units of time.