Welcome to Westonci.ca, your go-to destination for finding answers to all your questions. Join our expert community today! Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.
Sagot :
Certainly! Let's solve the given proportion step-by-step:
We need to determine the number of days, [tex]\( x \)[/tex], required to complete the entire project if 17.5 days are needed to complete [tex]\(\frac{3}{8}\)[/tex] of the project. The given proportion is:
[tex]\[ \frac{17.5 \text{ days}}{\frac{3}{8} \text{ project}} = \frac{x \text{ days}}{1 \text{ project}} \][/tex]
First, rewrite the proportion:
[tex]\[ \frac{17.5}{\frac{3}{8}} = \frac{x}{1} \][/tex]
For convenience, we will simplify the left side of the equation. Dividing by a fraction is the same as multiplying by its reciprocal. Hence, we have:
[tex]\[ \frac{17.5}{\frac{3}{8}} = 17.5 \times \frac{8}{3} \][/tex]
Next, calculate the product:
[tex]\[ 17.5 \times \frac{8}{3} = 17.5 \times 2.6666666666666665 \][/tex]
Now perform the multiplication:
[tex]\[ 17.5 \times 2.6666666666666665 \approx 46.666666666666664 \][/tex]
Thus, the number of days required to complete the entire project is:
[tex]\[ x = 46.666666666666664 \][/tex]
This means it will take approximately 46.67 days to complete the whole project if it takes 17.5 days to complete [tex]\(\frac{3}{8}\)[/tex] of it.
We need to determine the number of days, [tex]\( x \)[/tex], required to complete the entire project if 17.5 days are needed to complete [tex]\(\frac{3}{8}\)[/tex] of the project. The given proportion is:
[tex]\[ \frac{17.5 \text{ days}}{\frac{3}{8} \text{ project}} = \frac{x \text{ days}}{1 \text{ project}} \][/tex]
First, rewrite the proportion:
[tex]\[ \frac{17.5}{\frac{3}{8}} = \frac{x}{1} \][/tex]
For convenience, we will simplify the left side of the equation. Dividing by a fraction is the same as multiplying by its reciprocal. Hence, we have:
[tex]\[ \frac{17.5}{\frac{3}{8}} = 17.5 \times \frac{8}{3} \][/tex]
Next, calculate the product:
[tex]\[ 17.5 \times \frac{8}{3} = 17.5 \times 2.6666666666666665 \][/tex]
Now perform the multiplication:
[tex]\[ 17.5 \times 2.6666666666666665 \approx 46.666666666666664 \][/tex]
Thus, the number of days required to complete the entire project is:
[tex]\[ x = 46.666666666666664 \][/tex]
This means it will take approximately 46.67 days to complete the whole project if it takes 17.5 days to complete [tex]\(\frac{3}{8}\)[/tex] of it.
Visit us again for up-to-date and reliable answers. We're always ready to assist you with your informational needs. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. We're dedicated to helping you find the answers you need at Westonci.ca. Don't hesitate to return for more.