Find the best answers to your questions at Westonci.ca, where experts and enthusiasts provide accurate, reliable information. Get quick and reliable solutions to your questions from a community of experienced professionals on our platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.
Sagot :
Final answer:
To find the number of workers needed for a project in a different timeframe, use the formula Workers x Time = Constant Work.
Explanation:
To determine the number of workers needed to complete a project in a different timeframe, we can use the formula:
Workers x Time = Constant Work. This means that the amount of work required to complete the project remains constant.
Applying this formula to the given situation where 15 workers finish the job in 36 days, we have:
15 workers x 36 days = Total work to be done.
Then, to find the number of workers needed for 27 days, we use the constant work amount and the new timeframe, which gives us the number of workers needed.
Learn more about Workload calculation here:
https://brainly.com/question/38947403
We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. We're glad you visited Westonci.ca. Return anytime for updated answers from our knowledgeable team.