Welcome to Westonci.ca, the Q&A platform where your questions are met with detailed answers from experienced experts. Connect with a community of experts ready to help you find accurate solutions to your questions quickly and efficiently. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently.

You are managing a large, complex project that will take several years to complete. You are currently planning Phase 1 activities in detail and only planning the activities in later Phases at a high level. Which of the following planning approaches does this best describe?
A. Progressive Elaboration
B. Rolling Wave Planning
C. Agile Planning
D. Adaptive Planning