At Westonci.ca, we connect you with the answers you need, thanks to our active and informed community. Get detailed and precise answers to your questions from a dedicated community of experts on our Q&A platform. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.

In the agile project management approach:
a. Monitoring risks is likely to be performed within an iteration/sprint.
b. Monitoring risks happens immediately after an iteration/sprint ends.
c. Monitoring risks could result in changes to the product backlog.
d. Monitoring risks is done during the iteration/sprint daily standup.

Sagot :

Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. We're here to help at Westonci.ca. Keep visiting for the best answers to your questions.