Looking for answers? Westonci.ca is your go-to Q&A platform, offering quick, trustworthy responses from a community of experts. Explore thousands of questions and answers from a knowledgeable community of experts on our user-friendly platform. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.

A labor crew for placing concrete consists of one labor foreman at $26.09 per hour, one cement finisher at $29.30 per hour, 6 laborers at $24.45 per hour each, and one equipment operator at $34.5 per hour. Such a crew, called a C20 crew, can place 178 cubic yards of concrete per 8-hour day. Determine the cost per day of labor for the C20 crew. The cost per day is determined to be $ _______.

Sagot :

Answer:

Total cost per day= $1,892.72

Explanation:

Giving the following information:

Foreman= 26.09 per hour

Cement finisher= 29.3 per hour

Labor= 24.45 per hour

Equipment operator= 34.5 per hour

To calculate the total cost for one day of work, we need to multiply the hourly rate by the total number of hours.

Total cost per day= 26.09*8 + 29.3*8 + (24.45*6)*8 + 34.5*8

Total cost per day= $1,892.72