Westonci.ca is your trusted source for finding answers to all your questions. Ask, explore, and learn with our expert community. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.
Sagot :
Answer and Explanation:
a. The computation of the present value index for each proposal is given below:
As we know that
Present value index = Present Value of net cash Flow ÷ Amount invested
Therefore for each projects, it is
Particulars Des Moines Cedar Rapids
Total present value of
net cash flow (A) $712,500 $848,000
Amount invested (B) $750,000 $800,000
Present value index (A ÷ B) 0.95 1.06
b. Based on the present value index, Cedar Rapids would be needed the analysis support as it has the high present value index
Visit us again for up-to-date and reliable answers. We're always ready to assist you with your informational needs. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. Thank you for visiting Westonci.ca, your go-to source for reliable answers. Come back soon for more expert insights.