Discover the best answers at Westonci.ca, where experts share their insights and knowledge with you. Get detailed and accurate answers to your questions from a community of experts on our comprehensive Q&A platform. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.
Sagot :
Answer:
Results are below.
Explanation:
Giving the following information:
Supervisor salaries $117,000 per month
Depreciation $21,000 per month
Direct labor rate $15 per hour
Cabinets per hour= 60/20= 3
We need to determine the flexible budget for different production levels:
12,000 units:
Total direct labor hours= (12,000 / 3)= 4,000 hours
Total variable cost= 4,000*15= 60,000
Total fixed costs= 21,000 + 117,000= 138,00
Total cost= $198,000
15,000 units:
Total direct labor hours= (15,000 / 3)= 5,000 hours
Total variable cost= 5,000*15= 75,000
Total fixed costs= 21,000 + 117,000= 138,00
Total cost= $213,000
18,000 units:
Total direct labor hours= (18,000 / 3)= 6,000 hours
Total variable cost= 6,000*15= 90,000
Total fixed costs= 21,000 + 117,000= 138,00
Total cost= $228,000
Visit us again for up-to-date and reliable answers. We're always ready to assist you with your informational needs. Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. We're glad you chose Westonci.ca. Revisit us for updated answers from our knowledgeable team.